You can now Assign the durations and predecessors for all of the subtasks, including zero durations & predecessors for the milestones, BUT DO NOT ASSIGN EITHER DURATIONS OR PREDECESSORS FOR THE SUMMARY TASKS – allow the program to do this.
- Open Tutorial- 1
- Save as Tutorial 2: Uncheck Project Summary Bar (View Tab)
& DELETE PREDECESSORS (see NB below)
- Include Start Project, Slab Complete, Workshop Watertight, Power on, & Project Complete as MILESTONES within the Task List
- Include Concrete Slab, Workshop Structure, & Machines as
Summary Tasks on the list.
- Indent the subordinate tasks – (see page 5 Structure Notes )
- You can now Assign the durations and predecessors for all of the subtasks, including zero durations & predecessors for the milestones, BUT DO NOT ASSIGN EITHER DURATIONS OR PREDECESSORS FOR THE SUMMARY TASKS – allow the program to do this.
- Show task ID on the left for all bars
- Use Hide subtasks button, and show subtasks, show all subtasks
View Tab / Outline (Data Ribbon Group)
- Show Entire project on the monitor
- Save the project (Tutorial- 2)
Check on the Network Diagram and Calendar views – how have they changed?
- The Client has decided that the CLEAR SITE task must finish at the same time as
CONNECT & TEST MACHINES
What is the appropriate predecessor command? …………
What is the finish date now? —————–
How many days in total? ——————
- Save as Tutorial- 3