You can now Assign the durations and predecessors for all of the subtasks, including zero durations & predecessors for the milestones, BUT DO NOT ASSIGN EITHER DURATIONS OR PREDECESSORS FOR THE SUMMARY TASKS – allow the program to do this.

  1. Open Tutorial- 1

 

  1. Save as Tutorial 2: Uncheck Project Summary Bar (View Tab)

& DELETE PREDECESSORS (see NB below)

 

  1. Include Start Project, Slab Complete, Workshop Watertight, Power on,                      & Project Complete as MILESTONES within the Task List

 

  1. Include Concrete Slab, Workshop Structure, & Machines as

Summary Tasks on the list.

 

  1. Indent        the subordinate tasks – (see page 5 Structure Notes )

 

  1. You can now Assign the durations and predecessors for all of the subtasks, including zero durations & predecessors for the milestones, BUT DO NOT ASSIGN EITHER DURATIONS OR PREDECESSORS FOR THE SUMMARY TASKS – allow the program to do this.

 

  1. Show task ID on the left for all bars

 

 

  1. Use Hide subtasks button, and show subtasks, show all subtasks

View Tab / Outline (Data Ribbon Group)

 

  1. Show Entire project on the monitor

 

  1. Save the project (Tutorial- 2)

      Check on the Network Diagram and Calendar views – how have they changed?

 

  1. The Client has decided that the CLEAR SITE  task must finish at the same time as

CONNECT & TEST MACHINES

 

What is the appropriate predecessor command? …………

What is the finish date now? —————–

How many days in total? ——————

 

  1. Save as Tutorial- 3