Create a PERT/CPM network showing the interdependencies of the different activities. How long will the project take? (Note: Don’t forget to take elapsed time into account.)

1)The following table shows the allocation of work assignments and resources needed for an investment firm to make a decision on investing in company XYZ.

——————————-Task A—————-Task B————–Task C
Profolio Managers——-Week 1 (S)———————————Week 3 (P)
Associates——————————————Week 1 (P)——–Week 2 (S)
Analysts——————–Week 1 (P)———-Week 2 (P)——–Week 2 (S)
(P) =Primary (S)=Secondary

Resource Spreadsheet
Resource—————–Week 1————Week 2———Week 3
Profolio Manager———–1—————————————-1
Associates——————-1———————-2
Analyst————————2———————-5
Note: Figure in above spreadsheet are person-weeks of effort

a)Create Responsibility Matrix
b)Create Resource Gantt Chart
c)Create Resources Loading Chart

2) Building Swimming Pool, PD=Person days, ETD=Elapsed time days
Task—————-Worker——–PD—–# of workers—–ETD—–Material
Excavate———-Operator——-6————2—————–0——1500.00
Frame wall——–Masons——–8————4—————–0——–800.00
Install plumbing–Plumber——-4————2—————–0——–700.00
Install electricity–Electrician—-2————2—————–0——–500.00
Pour concrete—–Masons——-4————2—————–4——–2000.00
Install pump——-Plumber——-1————1—————–0——–3000.00
Total—————————————————————————–8500.00

Category————-Wage Rate $/Day
Electrician—————-200.00
Mason———————160.00
Machine Operator——120.00
Plumber——————-200.00

a)Create a Gantt chart from the work breakdown structure.
b)Create a PERT/CPM network showing the interdependencies of the different activities. How long will the project take? (Note: Dont forget to take elapsed time into account.)
c)Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a budget showing planned total expenditures for the project.